Senate permitting deal would make data centers pay twice for transmission
The bill overrides a 1994 FERC rule. Data centers would pay for new grid upgrades and for the existing network, and states could charge them even more.
Why it matters · Under current federal law, ordinary ratepayers are absorbing billions in grid upgrades built for data centers. This bill would change who pays, and with it how much transmission the AI boom ends up funding.
The Senate's bipartisan permitting deal includes several provisions that have drawn little attention. They would rewrite federal electricity law so that utilities and states can treat AI data centers and crypto miners differently from other large customers. Robinson Meyer calls it the "data center double tap."
The legal problem it fixes
Since the early 1990s, federal law has barred utilities from charging a customer both the incremental cost of transmission built for it and the embedded cost of the existing grid. The rule comes from a 1992 FERC case in which a utility tried to charge a neighboring generator both the normal grid rate and a congestion fee. FERC ruled that utilities had to charge whichever of the two was higher, and formalized the policy in 1994. The rule no longer applies to power plants, but it still covers customers.
Ari Peskoe of Harvard's Electricity Law Initiative says almost every utility now charges data centers the embedded rate. Utilities do this to avoid arguing over which upgrade costs count as incremental. The upgrades themselves then go into everyone's rates. According to a Union of Concerned Scientists report, customers in the country's largest power market paid $4.3 billion in 2024 for transmission upgrades serving data centers. Peskoe first pointed out that this rule makes the "new power delivery infrastructure" promise in Trump's March Ratepayer Protection Pledge nearly impossible to keep.