Local opposition has killed $260 billion of US data centers in 2026
Heatmap Pro data shows half of 2026's cancellations came in Q3, and about $1 trillion more in investment faces sustained local pushback.
Why it matters · Data center demand is a big driver of new load forecasts, grid buildout and power plant contracts. If local permitting is killing projects at this rate, demand forecasts and the generation and transmission plans built on them may be too high.
Large US tech companies are expected to spend more than $800 billion on data centers and AI this year. New figures from Heatmap Pro, Heatmap's market-intelligence service, show that local opposition is now cancelling a large share of that buildout.
The numbers
At least $260 billion in data center investment was canceled in 2026 after sustained local opposition. The pace is speeding up. About $130 billion, roughly half the year's total, was canceled in the three months ending September 30. In dollar terms, Q3 2026 cancellations alone were larger than all data center cancellations in 2025.
Around $1 trillion of data center investment now faces "sustained or meaningful" local opposition. Of the projects that ran into backlash this year, about half were ultimately canceled.
Heatmap says its figures are larger than other published estimates and are probably still an undercount, for two reasons:
- Only about 60% of data center projects disclose their planned investment. Disclosure is weakest at the early proposal stage, which is when projects are most likely to fail.
- The totals leave out some projects stalled by state-level moratoriums in Texas and New York.
How projects die
Heatmap Pro tracks cancellations through a continuous survey of public officials, regulatory filings and local media. Most canceled projects in its database died in one of two ways: they , or they ran into . now have a ban or moratorium on data center construction.